The City of Lewiston considers street rehabilitation on Meadow Drive, East Cedar Lane, Whispering Pine Court, West Main Street; Fremont Street to Meadow Drive, Riverside Drive; CSAH 25 to 350 feet west and East Street

Project Schedule

  • Resolution Ordering Preparation of Report – May 27, 2020
  • Prepare Feasibility Report – May 27, 2020 – June 10, 2020
  • Resolution Receiving Report and Calling for Hearing on Improvement – June 11, 2020
  • Published Notice of Hearing on Improvement – June 11, 2020 – June 18, 2020
  • Mailed Notice of Hearing on Improvement – June 12, 2020
  • Improvement Hearing – June 24, 2020
  • Resolution Ordering Improvement and Preparation of Plans and Specifications – June 24, 2020
  • Prepare Plans and Specifications– June 10, 2020 – June 24, 2020
  • Resolution Approving Plans and Specifications and Ordering Advertisement for Bids – June 24, 2020
  • Advertise for Bids – June 25, 2020
  • Open Bids – July 7, 2020
  • Resolution Awarding Contract – July 8, 2020
  • Begin Construction – Mid July 2020
  • End Construction – September 30, 2020
  • Final Assessment Hearing – October 15, 2020